Projects
Ongoing Projects
Building projects
Complete renovations on Athletic Hall of Fame – April 1 – May 1, 2019
Construction of new Welcome Wall – May 15 – August 15, 2019
University Hall flooring replacement – May 6 – May 26, 2019
Innovation Building flooring abatement – May 20 – June 1, 2019
Innovation Building flooring replacement – June 3 – June 21, 2019
Innovation Building drain line repairs – May 6 – June 1, 2019
Innovation Building first floor bathroom renovations – May 6 – June 1, 2019
Rahall house roof replacement – April 8 – April 12, 2019
Athletic Administration house roof replacement – April 15 – April 19, 2019
Admissions house roof replacement – April 22 – May 3, 2019
Administration & Extension roof replacement – May 6 – Aug 15, 2019
Interdisciplinary Science Building renovation – April 15 – December 31, 2019
Carter Hall roof top air handler units – May 6 – May 17, 2019
Carter Hall fitness room renovation – May 6 – June 6, 2019
Carter Hall electrical on roof – May 6 – May 10, 2019
Athletic batting cages behind guest house – May 13 – June 17, 2019
Hogan Hall lounge renovations – May 13 – June 17, 2019
Van Meter Gym wood floor refinishing – May 6 – May 10, 2019
Benedum window replacement – May 6 – May 17, 2019
LRC roof replacement – May 6 – August 15, 2019
LRC main stairwell window replacement – June 1 – June 15, 2019
LRC-314 renovation E-sports renovation – May 13 – August 15, 2019
LRC-324 faculty development room renovation – May 13 – August 15, 2019
University Police Retaining Wall – May 6 – May 17, 2019
Main parking lot brick wall repair – May 20 – Jun 10, 2019
Installation of stainless steel shelves in restrooms – May 13 – August 15, 2019 (weekends)
Parking lot projects
Hogan Hall parking lot repairs – May 6 – May 24, 2019
Innovation back parking lot repair – May 6 – May 10, 2019
Interdisciplinary Science Building parking repair – May 6 – May 8, 2019